The Issue:
A switchgear manufacturer was setting up a new facility of about 10,000 m² to manufacture Ring Main Units (RMUs). The sheet metal fabrication machines were installed, but there was no production infrastructure: no assembly lines, no workstations, no storage, and no system to move parts and enclosures between fabrication and assembly.
The client needed a complete, lean production setup designed and delivered quickly so manufacturing could begin.
Suggested Solution:
- Assembly lines and roller conveyors for RMU assembly
- Ergonomic multi-level workstations for sub-assembly
- Supply trolleys and ton trolleys that deliver material to the line and from the line.
- Dedicated trolleys for sheet metal parts, panel doors and enclosures
- Kitting carts that bring components to each operator’s point of use
- Pallet racking for raw material and component storage
Design:
ADAPTIV managed the full cycle: site visit, needs analysis, engineering drawings, manufacturing, and on-site installation. Every station was designed around the client’s RMU assembly process and the material flow from fabrication to final assembly.
Results in Numbers:
- Area equipped: ≈ 10,000 m²
- Project duration: 5 months from first engagement to handover
- On-site installation: 3 months
- Workstations: 16
- Trolleys, flow racks and kitting carts: 130+
- Assembly lines and conveyors: 2
- Outcome: The client went from zero production to a fully operational RMU assembly facility
Customer Feedback:
"ADAPTIV took our new facility from an empty floor to a working production line in a few months. Their team understood our process, designed every station around it, and delivered a flexible setup we can adapt as we grow."
Pictures After Implementation.
Other case studies
See all case studies- Engineering
Door Trolley for a Leading Automotive Manufacturer
ADAPTIV mobile door trolley: 12 doors upright, one per slot, roller deck; no contact damage; push/tow as one — safer, faster.

- Implementation
Workstations & Trolleys
64 customized units delivered in 3 months to support a wiring systems manufacturer's production expansion.